01 · Developers · Epping Forest
One house became three. Then the real work started.
North Weald Bassett, Epping · Epping Forest District Council · Developer client

- Project
- Part demolition, extension and conversion of a three-bedroom house into two semi-detached four-bedroom houses, plus a new detached four-bedroom house. Existing garage demolished.
- Planning
- Granted 29 November 2024, with a section 106 agreement and conditions
- Conditions
- Details for conditions 3, 4, 5, 6, 7, 15 and 19 submitted; decision 1 July 2025
- Our role
- Technical design and full construction drawings, discharge of conditions, CDM risk assessment, drawing issue control, support on site [confirm scope]
- Status
- Under construction [confirm / add completion date]
The brief
A single three-bedroom house on a generous plot outside Epping, and a developer who could see three homes on it: the existing house split and extended into a pair of semi-detached four-bedroom houses, and a new detached house alongside. Planning permission was granted in November 2024 [confirm whether the planning application was ours].
The obstacle
A permission is not a licence to start. This one came with a section 106 agreement and a string of pre-commencement conditions — surface-water drainage, a tree protection plan and arboricultural method statement, site set-up, materials — each of which has to be submitted, negotiated and formally discharged before a spade goes in. Developers lose months here, usually because the conditions are treated as paperwork rather than design.
What we did
We treated the conditions as the first stage of construction, not the last stage of planning. The drainage strategy, tree protection and site logistics were resolved together with the technical design, so the details submitted to the council were the details the builder would build from. Seven conditions went in as one application; the council issued its decision on 1 July 2025, with the drainage condition kept open for further detail [confirm current position].
Alongside that we produced the full construction set — plans, street elevations, sections, wall details — and the CDM risk assessment, and ran the drawing issue register so everyone on site was working from the current revision.
The outcome
Three houses being built from one address, with the council's conditions dealt with as part of the design rather than after it. [Add: completion date, sales or valuation outcome if the client is happy for us to say.]
1 → 3 homes on a single plot
From the record: Epping Forest District Council decision notices of 29 November 2024 and 1 July 2025.